Professional basement and foundation protection systems designed to prevent water penetration and structural dampness.
Surface Preparation
• Cleaning: Thoroughly Clean The Surface To Remove Oil, Dirt, Grease, And Loose Debris Using Wire Brushes Or Mechanical Grinding.
• Repair: Identify And Treat Honeycombs, Voids, And Protrusions. Cracks Should Be Widened Into A V-Groove And Filled With Non-Shrink Mortar.
• Coving/Angle Fillet: Apply 50mm X 50mm Angle Fillets At The Junction Of The Floor Slab And Vertical Walls Using Polymer-Modified Mortar To Eliminate Sharp 90-Degree Corners Where Stress Accumulates.
Joint Treatment & Grouting
• Injection Grouting: Fix PVC Nozzles At Construction Joints And Inject Cement Slurry Mixed With Non-Shrink Admixtures At Approximately 40 PSI To Seal Internal Voids.
• Waterbars: For New Constructions, Install Hydro-Swelling Waterbars (E.G.,) In Construction Joints Before Casting The Next Concrete Pour.
- Coal Tar Epoxy:Once The Waterproofing Is Cured, Apply Two Coats Of Coal Tar Epoxy Or Polyurea. This Is Vital To Protect The Concrete From The Corrosive Nature Of Sewage, Acids, And Sulphates.
- Curing:Allow The System To Air-Cure For At Least 7 Days Before Commissioning The Tank.